Operational Projects

LANDMARK WORKS

Completed six-lane highway with signage, NH-130-CD Odisha Active
Completed six-lane highway, NH-130-CD Elevated viaduct through mountains, NH-130-CD Six Lane Kandili aerial view Six Lane Kandili construction Six Lane Kandili progress

Six-Lane Kandili-Tumbigura, NH-130-CD

Raipur - Visakhapatnam Economic Corridor

Type 6 Lane HAM Highway
Location Kandili-Tumbigura, Odisha
Authority NHAI - Bharatmala Pariyojana
Status Active - Ahead of Schedule
10,74,460 Cum

Excavation — 3 months ahead of schedule

6-Lane HAM Highway under Bharatmala Pariyojana — a critical link in the Raipur–Visakhapatnam Economic Corridor. During 2023-24, Mana executed 10,74,460 Cum of open excavation ahead of the stipulated timeline, alongside 2,96,000 Cum of tunnel underground excavation and 1,60,000 Cum of concrete adherence.

  • 2,96,000 Cum tunnel underground excavation executed
  • 1,60,000 Cum concrete placed within scheduled timeframe
  • Full EPC execution with Mana's own 400+ equipment fleet
Twin tunnel portals under construction, Kadapa Expressway Active
Twin tunnel portals, Kadapa Expressway Tunnel interior with SCHWING shotcrete, Kadapa Aerial road embankment, Kadapa Bengaluru-Vijayawada expressway aerial Bengaluru-Vijayawada expressway progress

Bengaluru-Vijayawada Six-Lane Greenfield Expressway

Kavulakunta Section — Package 09

Project Bharatmala Pariyojana Phase-I, NH 544G
Location Kadapa Dist, AP
Client MAX INFRA PVT LTD / NHAI
Status Active - In Progress
20,50,000 Cum

Excavation in 6 months · ahead of NHAI timeline

Six-lane access-controlled greenfield expressway, Kadapa segment NHAI - Bharatmala Phase-I. 20,50,000 Cum excavation & embankment completed in just 6 months (May–Oct 2025) — all open earthwork finished ahead of stipulated NHAI timeline. 50 Nos. 36-metre girders erected within 2 months, reflecting exceptional productivity.

  • 50 Nos. 36-m girders erected in just 2 months — high productivity & precision
  • Tunnel underground excavation progressing ahead of schedule
  • Full compliance with NHAI specs — strict quality & safety protocols throughout
Massive tunnel interior with construction vehicles, Polavaram Active
Tunnel interior, Polavaram Tunnel portal with crane, Polavaram Dam barrage aerial view, Polavaram Twin tunnels Pkg-63 & Pkg-64 Twin tunnels construction

Twin Tunnels Pkg-63 & Pkg-64

Indira Sagar Polavaram Project

Scope 900M X 2, 800M X 2 twin tunnels
Capacity 20,000 → 40,000 Cusecs
Method NATM - Tamrock DT-820
Status Pkg 63 completed ahead of target, Pkg 64 in progress, ahead of schedule
19.35m × 19.35m

Asia's largest irrigation tunnel diameter

EPC execution of twin NATM tunnels for India's landmark Polavaram Irrigation Project. From Mar 2025 to Feb 2026: ~10,00,000 Cum excavation and ~1,56,400 Cum concrete for gantry & invert lining — completed 5 months ahead of schedule. CM Chandrababu Naidu personally acknowledged the scale and quality during a site visit.

  • ~10,00,000 Cum excavation + ~1,56,400 Cum concrete (Mar 2025 – Feb 2026)
  • Pkg-63: completion advanced from Aug 2026 → Mar 2026 — 5 months early
  • CM Chandrababu Naidu site visit — acknowledged scale & quality
Excavation with dump trucks at Yavatmal-Nanded Railway site Operational
Excavation with dump trucks, Nanded Railway Rock excavation close-up, Nanded Railway Railway site progress, Nanded Railway

New Broad-Gauge Railway Line, KM 157-169

Scope

Scope Construction of Bridges and Special structures, Earthworks excavations
Duration 9 Months
Client RVNL - Central Railway
Certificate RVNL Performance Certificate
15,00,000 Cum

Excavation completed in 9 months

Mana Infrastructure executed approximately 15,00,000 Cum of excavation for the Yavatmal-Nanded New Broad-Gauge line (Package-3A) under RVNL, completing the work within 9 months from May 2024 to February 2025. Originally given 6 months to complete 4,00,000 Cum of deep excavation as per the subcontract agreement dated 01/06/2024. Delivered in just 3 months — meeting the full target in half the stipulated time. In recognition of superior performance, RVNL issued us a Performance Certificate.

  • Road bed, Major & Minor Bridges, ROBs, RUBs, HI, Platforms
  • RVNL Performance Certificate issued

OTHER PROJECTS

Ongoing and Recently Completed Projects Across Various Sectors

HNSS Irrigation Canal Lining, Madanapalli
Madanapalli project 1 Madanapalli project 2 Madanapalli project 3
Irrigation

Madanapalli — HNSS Irrigation

STP Plant Construction, Haveri
Haveri project Haveri project 1 Haveri project 2
Water Treatment

Haveri — STP Plant

Musi Irrigation Excavation, Bhuvanagiri
Bhuvanagiri project 1 Bhuvanagiri project 2 Bhuvanagiri project 3
Irrigation

Bhuvanagiri — Musi Irrigation Project

EXECUTED WORKS

# Project Location Sector
01 H.N.S.S. Project Package-31 Anantapur, Andhra Pradesh Irrigation
02 Mundragi Branch Canal Koppal, Karnataka Irrigation
03 H.N.S.S. Project Packages 28 & 29 Kurnool, Andhra Pradesh Irrigation
04 Thottapalli Barrage Package-1 Balance Works Vizianagaram, Andhra Pradesh Irrigation
05 Paleru Reservoir Project Ongole, Andhra Pradesh Irrigation
06 Jurala Parallel Canal Atmakur, Telangana Irrigation
07 JLNSS Project Packages 100, 106 & 108 Peddapalli, Telangana Irrigation
08 H.N.S.S. Project Packages 54, 57 & 58 Anantapur, Andhra Pradesh Irrigation
09 Kistlapur Canal Gajwel, Telangana Irrigation
10 JCR-DLIS Phase-3, Package-4 Warangal, Telangana Irrigation

CURRENTLY ACTIVE

Major Projects Across India

NH 130-CD 100-OD NH-544G Bengaluru-Vijayawada Yavatmal-Nanded Railway Polavaram Tunnel Pkg 63 Polavaram Tunnel Pkg 64 STP Haveri Musi MLCJ NH 130-CD 100-OD NH-544G Bengaluru-Vijayawada Yavatmal-Nanded Railway Polavaram Tunnel Pkg 63 Polavaram Tunnel Pkg 64 STP Haveri Musi MLCJ
Recognition & Milestones

ACHIEVEMENTS

2023-24 · Odisha · NH 130-CD Package OD-08

10,74,460 Cum Excavation — 3 Months Ahead of Schedule

Mar 2025 – Feb 2026 · Andhra Pradesh

Package 63 (Polavaram Irrigation) — Asia's Largest Tunnel (19.35m × 19.35m) — received certification of achievement — CM Appreciation — 5 Months Early

May – Oct 2025 · Kadapa, AP · NH-544G Package-09

20,50,000 Cum in 6 Months + 50 Nos. 36m Girders in 2 Months

May 2024 – Nov 2024 · Maharashtra · RVNL

15,00,000 Cum completed in 9 months; 4,00,000 Cum deep excavation delivered in 3 months against a 6-month stipulation